Topic History of : Free PMP Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
7 years 11 months ago #7305

Paul M.

's Avatar

I think you meant B not A.
7 years 11 months ago #7300

Sindhya Sudheendran

Sindhya Sudheendran's Avatar

So the correct answer is B, not A.
7 years 11 months ago #7282

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

You are managing a shopping complex construction project. You have carried out a number of similar projects in the past and you want to outsource the electrical work to a contractor company. The last time you used a Cost Plus Fixed Fee contract but you were not satisfied with this approach because you didn't have much control over the outsourced work. What should you do this time to ensure that you have more control over the outsourced work?

A. Micro-manage the contractor's project management processes
B. Use a Cost Plus Incentive Fee Contract (CPIF)
C. Use a Teaming Agreement
D. Change the contractor

HINT: You have to make sure that the performance of the contractor is better this time.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

Using a Cost Plus Incentive Fee contract will help you control the contractor.