Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which of the following elements constitute the scope baseline?

A. Scope Statement, WBS, and Project Schedule
B. Scope Statement, Project Schedule, and WBS Dictionary
C. WBS Dictionary, Resource Calendars, and Project Schedule
D. Scope Statement, WBS, and WBS Dictionary

HINT: The Scope Baseline should contain the scope and related work information.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com.We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is D.

The Scope Baseline contains the Scope Statement, the WBS, and the WBS Dictionary.