Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
You are working at a steel manufacturing company as a project manager. There is a department called Welding and Fabrication in your company. You are getting ready to put together your project team and you want to see a hierarchical representation of how many welders are working for your company in the Welding and Fabrication Department. Which of the following illustrates this information?
A. Work Breakdown Structure
B. Organizational Breakdown Structure
C. RACI Chart
D. Resource Breakdown Structure
HINT: A welder is a resource. The project manager wants to see all welding resources in a hierarchical format.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
A Resource Breakdown Structure is a hierarchical structure of resources broken down by resource category and resource type.