NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: When do you perform stakeholder analysis?

When do you perform stakeholder analysis? 2 years 4 weeks ago #5781

  • Rachel
  • Rachel's Avatar Topic Author
  • Visitor
  • Visitor
The question is from head first labs free exam.

When do you perform stakeholder analysis?

A When managing communications on your project
B When developing the project charter
C When creating the project management plan
D When putting changes through change control

When do you perform stakeholder analysis? 2 years 2 weeks ago #5822

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 268
  • Karma: 7
  • Thank you received: 60
Hi Rachel,
stakeholder analysis is, according to the PMBOK, A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
the output of stakeholder analysis is part of the stakeholder management plan which in turn is part of the project management plan.

I would select option C as the best answer. (option A was correct as per the 4th edition however in the fifth edition stakeholder management plan is separated from the communication management plan)
The following user(s) said Thank You: Jideofor Ebeogu
Ahmed Amin Abdullah, PMP
Community Moderator
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

×
Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 5 Weeks of Live Coaching for just $49. Learn More...