TOPIC: When do you perform stakeholder analysis?

When do you perform stakeholder analysis? 1 year 3 months ago #5781

  • Rachel
  • Rachel's Avatar
The question is from head first labs free exam.

When do you perform stakeholder analysis?

A When managing communications on your project
B When developing the project charter
C When creating the project management plan
D When putting changes through change control

When do you perform stakeholder analysis? 1 year 3 months ago #5822

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Online
  • Moderator
  • Posts: 191
  • Thank you received: 41
  • Karma: 7
Hi Rachel,
stakeholder analysis is, according to the PMBOK, A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
the output of stakeholder analysis is part of the stakeholder management plan which in turn is part of the project management plan.

I would select option C as the best answer. (option A was correct as per the 4th edition however in the fifth edition stakeholder management plan is separated from the communication management plan)