NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: Question When do you perform stakeholder analysis?

When do you perform stakeholder analysis? 2 years 11 months ago #5781

  • Rachel
  • Rachel's Avatar Topic Author
  • Visitor
  • Visitor
The question is from head first labs free exam.

When do you perform stakeholder analysis?

A When managing communications on your project
B When developing the project charter
C When creating the project management plan
D When putting changes through change control

When do you perform stakeholder analysis? 2 years 11 months ago #5822

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 8
  • Thank you received: 72
Hi Rachel,
stakeholder analysis is, according to the PMBOK, A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
the output of stakeholder analysis is part of the stakeholder management plan which in turn is part of the project management plan.

I would select option C as the best answer. (option A was correct as per the 4th edition however in the fifth edition stakeholder management plan is separated from the communication management plan)
The following user(s) said Thank You: Jideofor Ebeogu
Ahmed Amin Abdullah, PMP
Community Moderator

When do you perform stakeholder analysis? 3 months 4 weeks ago #13289

  • Ram
  • Ram's Avatar Topic Author
  • Visitor
  • Visitor
I would like to differ from the option C because managing communicatons itself would need a plan. By the time you are into managing communications/plan, you should have known your stakeholders on who is how. Project Chart. Plan would be probably correct but if Define Scope was given as an option, that would be the right answer as thats when you would analyze your stakeholders from requirements and boundary perspective

When do you perform stakeholder analysis? 3 months 1 week ago #13577

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
When you develop project charter and defining scope

When do you perform stakeholder analysis? 2 weeks 1 day ago #14309

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
answer B in my view

stakeholder analysis is to done before any plan planning process starts i.e.. during identify stakeholders (Initiation process group)
also it is done throughout the project
Please correct me If I am wrong
  • Page:
  • 1
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonTracy Shagnea, PMPGenevieve Pluviose, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on July 14/15 for just $179. Learn More...