Question:

During which project management process will you manage procurement relationships and monitor contract performance?

A. Conduct Procurements
B. Control Procurements
C. Close Procurements
D. Plan Procurement Management


Hint: This must be a process from the Monitoring and Controlling Process Group.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is B.

As you want to manage the procurement relationships and monitor control performance, this must be a process from the Monitoring and Controlling process group. Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed. "Control Procurements" is the correct answer to this question.
Last edit: by Anne B.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login