Welcome, Guest
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 2 years 5 months ago #4227

  • Anne B
  • Anne B's Avatar

You are currently performing quality assurance on your project by conducting a Quality Audit. Which of the following is not an objective of a Quality Audit?

A. Share the good practices introduced or implemented in similar projects in the organization and/or industry
B. Document the effectiveness of the Risk Management process
C. Identify all the good/best practices being implemented
D. Identify all the gaps/shortcomings

Hint: Think about the specific knowledge area in which you conduct the Perform Quality Assurance process.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:http://free.pm-exam-simulator.com

The Correct Answer is B.

The Perform Quality Assurance process is conducted in the Quality Management knowledge area, not the Risk Management knowledge area. Although documenting the effectiveness of the Risk Management process is an important activity, it is performed in the Risk Management knowledge area, not the Quality Management area. All remaining answer choices are specific objectives of the Quality Audit.
Moderators: Yolanda Mabutas, Ahmed Amin, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Mark Wuenscher, PMP