fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: PMI-ACP Question of the Week!

PMI-ACP Question of the Week! 9 years 7 months ago #5211

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Free PMI-ACP Exam Sample Question (Artifacts)

Agile project management and product development uses several different types of documents specific to each iteration, which are referred to as "artifacts". All of the following are Agile iteration artifacts except:

A) Iteration Vision Statement
B ) Iteration Backlog
C) Iteration Plan
D) Iteration Burnup Chart

________________________________________

Free PMI-ACP Exam Sample Question 03 (Artifacts)

Correct Answer: A

The four main artifacts used in Agile project management and product development are the Iteration Plan, Iteration Backlog, Iteration Burndown Charts and Iteration Burnup Charts. The only type of "vision statement" used as an artifact in Agile is the Product Vision Statement. The "Iteration Vision Statement" is a completely fake term that we made up for this question.

Reference: The Software Project Manager's Bridge to Agility, Michele Sliger & Stacia Broderick, 2008.
Last edit: by Anne B.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinSameer MendaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login