Correct Answer to Q#44: D

Answer and Explanations:

Answer A: Incorrect. Participative leadership is often called democratic leadership and involves soliciting the input of team members and peers. However, the responsibility of making the final decision rests with the participative leader.

Answer B: Incorrect. Autocratic leadership involves allowing leaders to make decisions alone without the input of others. Autocratic leaders possess total authority and impose their will on the team.

Answer C: Incorrect. Transformational leadership depends on high levels of communication from management to meet goals. Leaders motivate employees and enhance productivity and efficiency through communication and high visibility.

Answer D: Correct. Servant leadership is the practice of leading through service to the team, by focusing on understanding and addressing the needs and development of the team members in order to enable the highest possible team performance.

Exam Reference: Agile Practice Guide, Project Management Institute Inc., 2017, Page(s) 33-38,154; see also Coaching Agile Teams: A Companion for ScrumMasters, Agile Coaches, and Project Managers in Transition, Lyssa Adkins, 2010
11 months 3 weeks ago #30387

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

Question 44: In an effort to increase agile knowledge, traditional project managers of a company have been paired with scrum masters to observe them lead their teams. One observation is that many project decisions are the responsibility of the project team and the scrum master is more facilitative than authoritative. In fact, the scrum masters seem more focused on ensuring that the team can focus on the work, have a shared vision, and determine how they will accomplish their work. What leadership approach have the scrum masters adopted?

A. Participative leadership
B. Autocratic leadership
C. Transformational leadership
D. Servant leadership
11 months 3 weeks ago #30380

Sameer Menda

Sameer Menda's Avatar

Correct Answer to Q#43: B

Explanations:

Answer A: Incorrect. The team and the relevant project stakeholders define the definition of done, which applies to every item in the backlog. The team, however, does not determine when a product or a product increment is complete.

Answer B: Correct. The product owner accepts the completed product increment in the iteration review meeting after reviewing the acceptance criteria and verifying the functionality.

Answer C: Incorrect. The sponsor can recommend product backlog items to the product owner, but a sponsor typically does not have the authority to accept or reject a product.

Answer D: Incorrect. The agile coach may facilitate the meeting where the product increment is reviewed. Accepting or rejecting the product, however, is not among the agile coach's responsibilities.


Exam Reference: Agile Estimating and Planning, Mike Cohn, 2005, Agile Team Roles - Product Owner
1 year 1 day ago #30374

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

Question 43: An agile team is demonstrating a recently developed product. Who determines when a product is complete?

A. The development team
B. The product owner
C. The sponsor
D. The agile coach
1 year 4 days ago #30368

Sameer Menda

Sameer Menda's Avatar

Correct Answer to Q#42: B

Team Evaluation, Individual Evaluation and Process Tailoring are all methods of soliciting feedback from your Agile project team members. Prototyping is a form of "Product" feedback, not a form of "Project Team" feedback.

Reference: Disciplined Agile Delivery: A Practitioner's Guide to Agile Software Delivery in the Enterprise, Scott W. Ambler, Mark Lines, 2012.
1 year 1 week ago #30356

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

Question 42: All of the following are considered methods of receiving feedback from Agile project team members except?

A ) Team Evaluation
B ) Prototyping
C ) Individual Evaluation
D ) Process Tailoring