TOPIC: Free CAPM® Exam Sample Question

Free CAPM® Exam Sample Question 4 years 7 months ago #20630

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies:

A. A start-to-finish relationship with a 2-day lead
B. A start-to-start relationship with a 2-day lead
C. A start-to-finish relationship with a 2-day lag
D. A start-to-start relationship with a 2-day lag
HINT: Note the difference between lead and lag.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is D

A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity. Thus, if the development team could start resolving issues two days after the testers started testing, it means that the two tasks have a start-to-start or SS relationship with a 2-day lag.

Details for each option:

A. A start-to-finish relationship with a 2-day lead
Incorrect. A situation where bug fixing can start 2 days after testing is a start-to-start relationship.

B. A start-to-start relationship with a 2-day lead
Incorrect. Lead is the amount of time that a successor activity can be advanced from a predecessor activity. In this case, it is a start-to-start relationship where the successor activity is being delayed, not advanced.

C. A start-to-finish relationship with a 2-day lag
Incorrect. Bug fixing can start 2 days after testing starts is a start-to-start relationship.

D. A start-to-start relationship with a 2-day lag
Correct. Lag is the amount of time that the second activity can be delayed with respect to the previous activity. Thus, the question scenario describes a start-to-start relationship with 2- day lag.

Reference: Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 192-193
Last edit: by John Paul Bugarin.