fbpx

Reply: Free CAPM® Exam Sample Question

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free CAPM® Exam Sample Question

Max. showing the last 6 posts - (Last post first)
4 years 2 months ago #20013

Arjie Maghanoy

Arjie Maghanoy's Avatar



Which value is not used to calculate the estimated duration using three-point estimating techniques?

A. Most likely estimate
B. Standard estimate
C. Optimistic estimate
D. Pessimistic estimate

HINT: Look for the estimate that is not mentioned in the PMBOK® Guide.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is B

Most likely, optimistic, and pessimistic estimates are the three types of estimates used to define an approximate value and range for an activity's duration using three-point estimating techniques.

Details for each option:

A. Most likely estimate
Incorrect. The most likely estimate is one of the three values.

B. Standard estimate
Correct. 'Standard estimate' is not a PMBOK® Guide term.

C. Optimistic estimate
Incorrect. The optimistic estimate is one of the three values.

D. Pessimistic estimate
Incorrect. The pessimistic estimate is one of the three values.

Reference: Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 201

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login