fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free CAPM® Exam Sample Question of the Week

Free CAPM® Exam Sample Question of the Week 4 years 10 months ago #17656

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Assess your readiness and answer this CAPM® Exam Sample Question of the brought to you by The CAPM® Exam Simulator

Which of the following is not included in the risk register?

A. Revised stakeholder tolerance
B. A list of identified risks
C. Prioritized list of quantified risks
D. Potential responses to identified risks

Exam Hint: Remember that the risk register is created in the Identify Risks process and will be updated in other risk management processes as the project progresses.

Watch out for the Answer here by the end of the week...
Last edit: by Rachel Madrid.

Free CAPM® Exam Sample Question of the Week 4 years 10 months ago #17688

  • Martin Premont
  • Martin Premont's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 42
  • Thank you received: 3
C Quantified risks are optional after qualitative risk analysis and if needed.

Free CAPM® Exam Sample Question of the Week 4 years 10 months ago #17734

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Correct Answer: A

Stakeholder tolerance, when applied, is revised in the Plan Risk Management process and documented in the risk management plan, not in the risk register.
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more CAPM exam sample questions? Simply sign up to our Free PMP Exam Simulator by visiting free.pm-exam-simulator.com/ where we offer updated questions.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI)®. As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI® established quality assurance criteria.

“PMI” and “CAPM” are registered marks of Project Management Institute, Inc.
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login