Correct Answer: B

A finish-to-start logical relationship is one in which is successor activity cannot start until a predecessor activity has finished. This logical relationship is the most common and is often the default.


All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more CAPM® exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.
5 years 7 months ago #15054

Anonymous

's Avatar

Finish to start
5 years 7 months ago #15051

Rachel Madrid

Rachel Madrid's Avatar

Assess your readiness and answer this CAPM® Exam Sample Question of the week taken from our newly launched CAPM® Exam Simulator!

You are using the precedence diagramming method to sequence the project schedule activities in your activity list. Of the following logical relationships between project activities, which is the most common?

A. Finish to finish
B. Finish to start
C. Start to start
D. Start to finish

Hint: By default, no project activities overlap, and each task must be completed before the next one can begin.

Answer will be posted by the end of the week!