Correct answer is A!
In project change management, a change control board (CCB) may be required to review and approve for changes. Normally, members of the change control board come from various departments to ensure the impact of change requests to all aspects of the project and other factors outside the project are considered and analyzed before making a decision.
***************************************************************
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more CAPM exam sample questions? Just go to
free.pm-exam-simulator.com
and try the PM Exam Simulator free for 7 days.
OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.