TOPIC: Why is 'The Define Scope process should only be executed during project planning' false?

Why is 'The Define Scope process should only be executed during project planning' false? 6 years 2 weeks ago #13832

  • Daniel Blossey
  • Daniel Blossey's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Por el placer de vivir viajando!
  • Posts: 32
  • Thank you received: 1
Planning processes can be iterative and develop over time (e.g. scope). But if there is another iteration (e.g. another project phase; 5th edition, page 45: "During an iteration, activities from all Project Management Process Groups will be performed.") then Define Scope is still executed during project planning.?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinCoy Studer

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login