3 years 3 months ago #25216

Harry Elston

Harry Elston's Avatar

Sharon,

Monte Carlo simulations or experiments are used for three general categories: System optimization, numerical integration and probability. For PMI's purposes and PMP Exam prep, they are used to create a probability distribution of a desired outcome. In that instance, the area around the desired outcome represents the uncertainty of the simulation. Do not get hung up on it, stick with the definition and explanation in the PMBOK Guide.

Harry
3 years 3 months ago #25201

Sharon S

Sharon S's Avatar

Isn't a Monte Carlo a representation of uncertainty as well as a simulation?


Posted in the wrong forum.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login