14 years 4 months ago #1001

Cornelius Fichtner

Cornelius Fichtner's Avatar

Michely,

The answer to your question is on page 431 of the PMBOK Guide, where you find the definition for the OPA in the Glossary. It says: "...any or all of the organizations involved in the project..."

Generally speaking: It doesn't matter where the OPA comes from. You need to consider all that influence your project no matter where they come from.
14 years 4 months ago #999

MICHELY T RIVAS

MICHELY T RIVAS's Avatar

Some times I get confuse in this kind of situations:

+ Mary is a Pj Manager in Enterprise A.
+ Enterprise A make software and have a good software process defined.(included Pj Managment)
+ Enterprise B make cars, and need a software product.
+ Enterprise B haver a IT department, they make software but in this case, they don´t want to doit.
+ Enterprise B is big and have a good software process defined (included Pj Managment)
+ Enterprise B hire Enterprise A to make a product software.
+ Enterprise A ask Mary to manage that project.

1. When the PMBOK talks about OPA, which OPA have mary to use? the one´s from her enterprise (A) or the one´s from the customer's enterprise (B)?

2. Who is the performer in this case? Enterprise B or Enterprise A?

Tks a lot.

Michely.