TOPIC: Question E 01.36 Completing Project Constraints

E 01.36 Completing Project Constraints 8 years 5 days ago #967

  • Chandrasekhar Botcha
  • Chandrasekhar  Botcha's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi,
In one of your example slide in E01.36.

You are asked a question based on the following situation:
Project is way behind schedule
No extra resources available
You have to implement all planned features
What will you do to meet the deadline?
You should be alloted more funds to hire more human resourced - X (No extra resources available
Scope of the project should be changed
but how scope change is the answer when there is condition that You have to implement all planned features.

Re:E 01.36 Completing Project Constraints 8 years 5 days ago #970

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1107
  • Karma: 35
  • Thank you received: 184
Chandrasekhar,

You are correct. That is indeed an error that needs to be fixed. Instead of "must implement all features" it should read "must implement at the required quality level".
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on Dec 02/03 for just $79. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM