Reply: Who can submit a change request?

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Who can submit a change request?

Max. showing the last 6 posts - (Last post first)
4 years 2 weeks ago #20338

David R

David R's Avatar

First of all, this is very valid question
To note: how are change requests implemented? You will recall change requests are outputs from many processes but MUST be approved through Integrated change control (Integration knowledge area) and Monitoring and Control process group. Approved updates are then implemented through Direct and Manage project work.
Therefore any stakeholder may ask a change depending on his power and influence and interest but his request must be thru change control board, of integrated change control process to be approved First
4 years 2 weeks ago #20334

Harry Elston

Harry Elston's Avatar

Riaz,

The short answer is "just about anyone can submit a change request." Stakeholders (including suppliers and subcontractors), team members, etc. are all there. In reality, however, corporate internal policies (found in the OPAs) will probably limit the list of those that can submit change requests..

Best,

Harry
4 years 2 weeks ago #20333

Riaz Hassan

Riaz Hassan's Avatar

Hi folks - this is a really straightforward question but I'm having trouble finding the straightforward answer. Per PMI standards, who is allowed to submit change requests? Any stakeholder? Any team member? Or must it be the PM?

Thx!