Hi Donald,
i am agree with defined definition -:
According to PMI, The project calendar is a "calendar that identifies working days and shifts that are available for scheduled activities." The project schedule is defined as an "output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources."
However in doubt with given example. Resource calendar- It identifies the working days, shifts, start and end of normal business hours, weekends and public holidays when each specific resource is available Information on which resources ( Such as team resources, equipment and material) are potentially during a planned activity period is used for estimating resource utilization. ( PMBOK - 373)
MY understanding says, if exam ask about resource availability then check with resource calendar rather then project calendar. Project calendar will have activity start and end date.