TOPIC: Acceptance Criteria in Requirements Traceability Matrix

Acceptance Criteria in Requirements Traceability Matrix 7 months 4 hours ago #17332

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Are "acceptance criteria" mentioned in the PMBOK (pg. 149) for the requirements traceability matrix specific to requirements or are they the same acceptance criteria found in the project scope statement?

Acceptance Criteria in Requirements Traceability Matrix 6 months 3 weeks ago #17403

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 3
  • Thank you received: 17
Yes they can be the same. The Requirements Traceability Matrix track requirements at an attribute level of a product to ensure that each requirement satisfy stakeholders' approved requirements specified in the Requirements Documentation.
The following user(s) said Thank You: Ben Chalfie
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...