Hi Joe,
That is very helpful thanks! Though there are some things I might need some extra clarification on.
I thought scope covered what could potentially be covered or not covered (out of scope) in the project, e.g. the scope of the project only entails building a car, and example of out of scope items would be maintenance or building a garage with that car.
With regards to requirements and change management, are requirements only cover "what needs to be done" initially? Are any changes to the requirements or "what needs" done after the initial stage covered under change management?
Best Regards,
Don