The exam simulator and prepcast documents say project charter is not a controlled document. Though the PMBOK guide does not list out which project document is controlled or not.
Why is project charter not a controlled document?
The project charter is an approved document that is signed by the project sponsor and authorizes the PM to commit the PM too begin the project and assign org resources. Based on the fact is a signed/approved/authorized document, should it not qualify as a controlled document? I understand the Charter is not baselined, but still approved nonetheless
Is there a PMBOK definition for what is a controlled document?