Dear all,
I do two PMP exam, but unfortunately, I did not pass.
In last exam I have get:
Initial : under target
Planning: above the target
Execution: need improvement
Monitoring and controlling: Target
Closing: above target
Anyway, after the exam I have written some of the questions related to the risk which these questions I am not sure about the answers
These the questions:
1- If you apply implemented risk , then what you need to do next?
2- During the project you find unforeseen risk, that happen because of:
3- Unforeseen risk happen and you apply workaround,. What you need to do next .
4- If you find unforeseen risk before it happen, what you need to do first?
5- After you implement the risk , your budget not enough to complete the project . this issue can be avoid if you do :
6- You work in area maybe the electricity will discount, you rent generator from shop, what type of this implementation. (Transfer or mitigate)
7- Some risk happen and you apply contingency plan , however the plan not work because these is no staff to apply it, this can be avoid if you do which of the following: