I know this may be a fundamental question but who approves (if any) the;

* Project Charter
* Project Management Plan

Also where is the benefits management plan created and who approves?

Project Charter and Project Management Plan Approvals 7 months 3 weeks ago #15477

  • Joe Pang
  • Joe Pang's Avatar
  • Away
  • Moderator
  • Moderator
  • Posts: 177
  • Karma: 11
  • Thank you received: 51
Hi KB,

For the project charter, it would be the project sponsor, and in some cases - the sponsor along with selected key stakeholders

For the project management plan, you should first find out what org structure of the company the project takes place. The plan is approved by the project sponsor and the key stakeholders (ex. functional managers who provides the resources for the project)

Hope this helps,
Joe
Toronto-based project manager, currently engaging in paperless transformation projects for utilities companies

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
21-Jun-2019: Free PMP Exam Coaching Webinar with Dan Ryan Register Now...