Configuration management deals with changes in product specifications. Change management is related with the process. Delay in a schedule , cost overruns are related with change management. To add a new feature to a product is related with configuration management. There is a good article related with the differences between
Configuration Mgmt vs. Change Mgmt
Anyone got any good tips or mnemonics on how to remember the different between change and configuration management? I've had a few practice questions come up on it and although I understand what both things are, I have a hard time defining the difference.
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®