Reply: Control Procurement VS Close Procurement

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Control Procurement VS Close Procurement

Max. showing the last 6 posts - (Last post first)
6 years 2 months ago #13238

Ty Weston, PMP

Ty Weston, PMP's Avatar

If I am not mistaken:
1. Payment claim dispute is done under close procurements. PMBOK 5, 12.4 Close Procurements.
2. Validating the deliverables of a contract would essentially be done in Control Procurements. This is where you monitor the performance and that both sides meet the requirements of that contract. PMBOK 5, 12.3 Control Procurements.
6 years 2 months ago #13212

CL

CL's Avatar

Hi,

I would like get some clarification on the following:

1) Do we negotiate or process payment/claim dispute under CONTROL Procurement (Claim administration) or CLOSE Procurement (Procurement Negotiation)?

2) In Project we have validate scope for acceptance of deliverables. What about in Procurement, do we validate seller work/deliverables under CONTROL Procurement or CLOSE Procurement?

Thanks.