TOPIC: Inquiry

Inquiry 9 years 2 months ago #11348

  • Anand Kakkar
  • Anand Kakkar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi,
I came across the following question,

Q: PM detects negative variance, what should he do FIRST
initiate a change request
OR
Perform Root cause analysis

My guess is Initiate a change request BUT incase the flaw is in the process, then will it not be good to improve the process first and then request a change

Please advise

thanks

Anand

Inquiry 9 years 2 months ago #11355

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Until the PM knows what change to make (recommend) there is no basis for a change request.

Thus, if those are the only two options, you have to choose doing a root cause analysis.

Best regards,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
The following user(s) said Thank You: Gail Freedman
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login