Procument Question 6 years 9 months ago #11250

  • Rick
  • Rick's Avatar Topic Author
  • Visitor
  • Visitor
The below is a question from RITAs Fastrack

Which of the following statements represents a fixed price incentive fee (FPIF) contract?

A. Pay $1,000,000.
B. Pay $1,000,000 plus $10,000 for every designated incremental quality level reached.
C. Pay all the costs plus a $10,000 fee.
D. Pay the costs plus $10,000 for every month the project is finished earlier than June 14.

Correct Answer:
B. Pay $1,000,000 plus $10,000 for every designated incremental quality level reached.

Is the correct answer D rather than B?

Procument Question 6 years 9 months ago #11251

  • John Wolverton
  • John Wolverton's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 118
  • Karma: 1
  • Thank you received: 27
No, on a fixed price contract you never pay cost. However you are paying the performance fee if they reach their goals. In this case $10,000 a increment.

Best Wishes
John F. Wolverton, PMP®
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login