Reply: Why is a cost budgeting tool an OPA?

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Why is a cost budgeting tool an OPA?

Max. showing the last 6 posts - (Last post first)
6 years 9 months ago #11104

Scott Smith

Scott Smith's Avatar

Thank you - very helpful!
6 years 9 months ago #11103

Ahmed Amin

Ahmed Amin's Avatar

cost budgeting tool is normally developed by the organization to maintain the resource prices, overhead costs, etc. hence it is an organizational process asst since it is "specific to and used by the performing organization".
Scheduling tool is normally a ready-made tool "not under the control of the project team" and is not specific to the organization as it is a general tool.
6 years 9 months ago #11090

Scott Smith

Scott Smith's Avatar

Why is this not an EEF like a scheduling tool?