Reply: Change Request process priority

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Change Request process priority

Max. showing the last 6 posts - (Last post first)
7 years 1 month ago #9659

Mark Wuenscher, PMP

Mark Wuenscher, PMP's Avatar

Senthil,
Not quite sure what you are asking. Yes, you would update the change log as part of the process.
Mark
7 years 2 months ago #9650

Senthilkumar Pachai

Senthilkumar  Pachai's Avatar

What about Change Log?
7 years 2 months ago #9566

Lawrence Li

Lawrence Li's Avatar

Thanks Mark, the procedure is clear and thanks
7 years 2 months ago #9550

Mark Wuenscher, PMP

Mark Wuenscher, PMP's Avatar

Lawrence,

A documented change request procedure might look something like below. The procedure for any particular project may be different than this. It really depends on the type and complexity of the project that is being managed.

Mark


Step #1: Identify the need for a change (Any Stakeholder)
Requestor will submit a completed change request form to the project manager
Step #2: Log change in the change request register (Project Manager)
The project manager will maintain a log of all change requests for the duration of the project
Step #3: Conduct an evaluation of the change (Project Manager, Project Team, Requestor) The project manager will conduct an evaluation of the impact of the change to cost, risk, schedule, and scope
Step #4: Submit change request to Change Control Board (CCB) (Project Manager)
The project manager will submit the change request and analysis to the CCB for review
Step #5: Change Control Board decision (CCB)
The CCB will discuss the proposed change and decide whether or not it will be approved based on all submitted information
Step #6: Implement change (Project Manager)
If a change is approved by the CCB, the project manager will update and re-baseline project documentation as necessary as well as ensure any changes are communicated to the team and stakeholders
7 years 2 months ago #9549

Lawrence Li

Lawrence Li's Avatar

Thanks Ahmed
7 years 2 months ago #9548

Ahmed Amin

Ahmed Amin's Avatar

Hi Lawrence,
the impact of the change is an important part of the CR document, this implies that you analyze and document the CR impact before issuing it.