fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Resource Calendar seems to be an output so late in the project, how could it be used in Planning in a timely manner?

Resource Calendar seems to be an output so late in the project, how could it be used in Planning in a timely manner? 7 years 3 months ago #9254

  • Bryan Ostrowski
  • Bryan Ostrowski's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
How is it that the resource calendar is an input to planning much earlier? It seems like the calendar would be an output much earlier so it can be used.... Wouldn't there be a delay to wrap up Estimates Activity Resources, Estimating Activity Duration, Develop Schedule, or Determine Budget?

Resource Calendar seems to be an output so late in the project, how could it be used in Planning in a timely manner? 7 years 3 months ago #9308

  • Bonnie
  • Bonnie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 29
  • Thank you received: 6
Surprised no one else commented on this.
To paraphrase Rita - I just read this today - The Acquire Project team should be viewed as Acquire "Final" Project Team. Early on in the Project timeline, some of the key teammates have already been assigned to assist with the important Planning Tasks you mention.

Hope that helps.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login