fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Management Reserves

Management Reserves 7 years 5 months ago #8912

  • KBG
  • KBG's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 15
  • Karma: 1
  • Thank you received: 4
Based on PMBOK, Management Reserves are not included in the cost baselines but is part of the overall budget and funding requirements.
Page 206

Question from PM PrepCast Simulator
The total authorized budget for your IT project is $160,000 and management reserves is $20,000. You want to measure cost performance to see how the project is doing. In this context, the cost performance is against measured which of the following budget amounts?
Answer is $140,000

Is the subtraction of MR because it's part of the authorized budget.

Thank you.

Management Reserves 7 years 5 months ago #8964

  • Kevin Nason
  • Kevin Nason's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 76
  • Karma: 3
  • Thank you received: 18
Kristin

That is correct. The key phrase to look at in this is the "Total Budget" I too got confused on this early in my studies.

Good Luck!
The following user(s) said Thank You: KBG
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login