Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Admin closure vs Contract closure

Admin closure vs Contract closure 7 years 3 months ago #516

  • KALU OGBUGO
  • KALU OGBUGO's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Karma: 0
What exactly are the differences between Administrative Closure vs Contract Closure? If encuntered in the exam what salient meanings can help me differentiate them?

Re:Admin closure vs Contract closure 7 years 3 months ago #517

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Kalu,

Contract closure: Closing a single contract on your project. (You may have 20 contracts going on, but you are only closing one).

Administrative Closure: Part of the Close Project or Phase process, in which you close your complete project when you are completely finished with everything, or when you close a phase (at the end of the phase.)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®