Admin closure vs Contract closure 7 years 1 month ago #516

  • KALU OGBUGO's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Karma: 0
What exactly are the differences between Administrative Closure vs Contract Closure? If encuntered in the exam what salient meanings can help me differentiate them?

Re:Admin closure vs Contract closure 7 years 1 month ago #517

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 966
  • Thank you received: 152
  • Karma: 29

Contract closure: Closing a single contract on your project. (You may have 20 contracts going on, but you are only closing one).

Administrative Closure: Part of the Close Project or Phase process, in which you close your complete project when you are completely finished with everything, or when you close a phase (at the end of the phase.)