TOPIC: Question Admin closure vs Contract closure

Admin closure vs Contract closure 8 years 1 month ago #516

  • KALU OGBUGO
  • KALU OGBUGO's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
What exactly are the differences between Administrative Closure vs Contract Closure? If encuntered in the exam what salient meanings can help me differentiate them?

Re:Admin closure vs Contract closure 8 years 1 month ago #517

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1100
  • Karma: 35
  • Thank you received: 183
Kalu,

Contract closure: Closing a single contract on your project. (You may have 20 contracts going on, but you are only closing one).

Administrative Closure: Part of the Close Project or Phase process, in which you close your complete project when you are completely finished with everything, or when you close a phase (at the end of the phase.)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 6 Weeks of Live Coaching for just $59 ($79 after October 27). Learn More...