Admin closure vs Contract closure 16 years 10 months ago #516

  • KALU OGBUGO
  • KALU OGBUGO's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
What exactly are the differences between Administrative Closure vs Contract Closure? If encuntered in the exam what salient meanings can help me differentiate them?

Re:Admin closure vs Contract closure 16 years 10 months ago #517

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 2066
  • Karma: 142
  • Thank you received: 698
Kalu,

Contract closure: Closing a single contract on your project. (You may have 20 contracts going on, but you are only closing one).

Administrative Closure: Part of the Close Project or Phase process, in which you close your complete project when you are completely finished with everything, or when you close a phase (at the end of the phase.)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: EM07
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login