TOPIC: Time management flow

Time management flow 3 years 10 months ago #8843

  • Andres Perez
  • Andres Perez's Avatar Topic Author
  • Visitor
  • Visitor
During planning in time planning the process are:
6.2 Define activities
6.3 Sequence activities
6.4 Estimate activity resources
6.5 Estimate activity duration
6.6 Develop schedule

Once 6.2 is done all the others (but mainly 6.3, 6.4 & 6.5) are sequential or parallel activities ?
Just for the questions "what is next or first"
To me, first is 6.2 then 6.3, 6.4 & 6.5 in parallel and then 6.6.
Is it right?

Time management flow 3 years 10 months ago #8845

  • Rahul Kakkar
  • Rahul Kakkar's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 161
  • Karma: 9
  • Thank you received: 52
That is correct Andres.
Rahul Kakkar, PMP, MBA
Community Moderator


How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login