A question from Cheetah learning prep test:
In which phase or phases is it BEST identify stakeholders and perform stakeholders analysis.
A. Iniciating
B. Executing
C. Planning
D. All phases in the Project Life Cycle
At first sight, identify stakeholders belong to initiation process group. Stakeholder analysis is a T&T of identify stakeholders, so A is clearly the right answer.
However, the right answer is D.
Cheetah's rational answer: Team members and stakeholders often change throughout a project. Therefore, you are always identifying stakeholders needs (new & old)
Is it the same for risks?
And for communications, requirements, HR, etc?