For the purpose of the PMP Exam: Scope Creep is defined as:

Adding features and functionality (project scope) without addressing the effects on time, costs, and resources, or without customer approval.

Outside of the PMP exam I have never heard the term used in regards to removing scope. I suppose this is mainly so because removing scope in an uncontrolled fashion is usually not a big problem. But adding scope in such a way is.

However, your question is an interesting one to ponder. But for the PMP exam you should not worry about it.
14 years 6 months ago #496

Anis Malouche

Anis  Malouche's Avatar

Hi all,

Does ''Scope Creep'' can be also used for a requested change from the customer for reducing the scope without going through the Integrated Change Control Process?

Or '' Scope Creep'' just apply for additional work?