Do you need customer support or technical assistance? Click here to submit a support ticket...
  • Page:
  • 1

TOPIC: lead and lag

lead and lag 8 months 1 week ago #8038

  • Hazem Ibrahim
  • Hazem Ibrahim's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 58
  • Thank you received: 2
Is it not more logic and make more sense to describe the FS relationship with a lead 30 days for example to be considered SS relationship with a lag 6 weeks for example .?what is the meaning to say its FS meanwhile it starts before the predecessor process finish actually?
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoRahul KakkarFernando Jr Sinlao LimMary Kathrine PaduaChris PreziottiLazard Toe, ITBMC, MPM, CIPM, PMP, ITILChristian WinterGail FreedmanKevin NasonMichael Sumaquial, PMPSteven Mudrinich, PMPMark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®