Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: M&C Risk question

M&C Risk question 7 years 2 months ago #479

  • Anis Malouche
  • Anis  Malouche's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 4
  • Karma: 0
Hi All,

Why should we include Work Performance information as an input in the
Monitor and Control Risk, since we have allready Performance Reports
as an Input?

My understanding is that Performance Reports include allready the same

Thank you,

Re:M&C Risk question 7 years 1 month ago #482

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Online
  • Administrator
  • PrepCast Instructor
  • Posts: 968
  • Thank you received: 152
  • Karma: 29

You are partially correct. According to the Glossary Performance Reports does include WPI but it also goes further than that because it includes Earned Value which is not part of the WPI. Also take a look at figure 11-20 where you can see that these 2 inputs come from 2 totally different processes.

So yes... there is definitely some overlap of the information in these 2 inputs and you could argue.

But remember... when it comes to the PMP Exam then the PMBOK Guide is always right. (I know that may not be a 100% satisfying statement, but it helps to pass the PMP exam.)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda Mabutas, Ahmed Amin, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Jeremy Raelin, Mary Kathrine Padua, Yasir Mehmood, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP