fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: M&C Risk question

M&C Risk question 14 years 8 months ago #479

  • Anis Malouche
  • Anis  Malouche's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hi All,

Why should we include Work Performance information as an input in the
Monitor and Control Risk, since we have allready Performance Reports
as an Input?

My understanding is that Performance Reports include allready the same
information.

Thank you,

Re:M&C Risk question 14 years 8 months ago #482

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Anis,

You are partially correct. According to the Glossary Performance Reports does include WPI but it also goes further than that because it includes Earned Value which is not part of the WPI. Also take a look at figure 11-20 where you can see that these 2 inputs come from 2 totally different processes.

So yes... there is definitely some overlap of the information in these 2 inputs and you could argue.

But remember... when it comes to the PMP Exam then the PMBOK Guide is always right. (I know that may not be a 100% satisfying statement, but it helps to pass the PMP exam.)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login