TOPIC: Question Estimate Cost Input - Why no project management plan

Estimate Cost Input - Why no project management plan 1 year 4 months ago #7481

  • Evan Janis
  • Evan Janis's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello everyone,
During my studies, I noticed that Plan Cost Management has the project management plan is an input, which makes sense as it includes the scope baseline. However in the Estimate Costs the Project Management Plan is not an input and rather just the Scope Baseline from within it is. Why not have the Project Management Plan as the input since its includes it as well?
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 6 Weeks of Live Coaching for just $59 ($79 after October 27). Learn More...