Dear Rahul
Thanks for your kindly clearification ,,,
It makes scenes , key deliverables (identifying) by PM and (carrying out) the activities to creat those deliverables by Team ...
On the project who is responsible for identifying key deliverables , based on business requirements , in order to manage customer expectations and direct the achievement of the project goals ?
I select D , but the answer is #Wrong , my justification was " Project staff are the members of the team who carry out the work of creating the project deliverables"
But the correct answer is A , based on the New Task 2: Emphasis on identifying key deliverables based on the business requirements, in order to manage customer’s expectations.