Reply: stakeholder

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : stakeholder

Max. showing the last 6 posts - (Last post first)
8 years 2 months ago #6767

Ahmed Amin

Ahmed Amin's Avatar

Totally agree with Tracy, competitors are not stakeholders but the risks that can result from the completion must be considered in the risk planning and management.
8 years 2 months ago #6759

Tracey South

Tracey South's Avatar

I will also add that while a Competitor is not a stakeholder they often need to be considered when assessing Risks to your project.

Tracey
8 years 2 months ago #6756

Mohit Saxena

Mohit Saxena's Avatar

Thanks Lazard.
Well explained.

Regards!!!
8 years 2 months ago #6754

Krishna

's Avatar

Stakeholder is somebody who wishes the project to be success.there may be negative staekholders but ultimately after the project is live it would be beneficial for them too.For competitior it would not be beneficial.Infact success of a project is threat for him
8 years 3 months ago #6753

Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL

Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL's Avatar

Hi Mohit,

"A stakeholder is an individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project. Stakeholders may be actively involved in the project or have interests that may be positively or negatively affected by the performance or completion of the project. Different stakeholders may have competing expectations that might create conflicts within the project. Stakeholders may also exert influence over the project, its deliverables, and the project team in order to achieve a set of outcomes that satisfy strategic business objectives or other needs"
The above statement is from the PMBOK (page 30) and it goes on to explain who is a stakeholder and does he relate with the project.
Competitor is not stakeholder because he does not play any role in the success or failure of your project. He may not be even aware of your project. He is external to your project.

Best regards.
8 years 3 months ago #6750

Mohit Saxena

Mohit Saxena's Avatar

Hello,
I have a question -
Competitor is a stakeholder or not?
Pls explain why?

Thanks!