TOPIC: Question Which process includes implementation of risk responses?

Which process includes implementation of risk responses? 1 year 11 months ago #6581

  • David Kornaros
  • David Kornaros's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Thank you received: 0
The PMBOK guide (p 349) reads “control risks is the process of implementing risk response plans, tracking…..”
However, PMPrepcast L11.06 (Control risks) says “Risk responses don’t stay in risk mgmt. We don’t actually execute responses here. That happens in the executing processes.”
These statements seem to be in conflict IMO. The PMBOK guide says that risk responses are implemented as part of Control Risks, but Cornelius implies the opposite.

Would appreciate clarity if I'm misunderstanding.
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on Dec 02/03 for just $79. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM