Beta distribution/PERT estimates 10 years 11 months ago #6555

  • Saeed
  • Saeed's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Hi
Which activities are best candidates for PERT estimates (O+4M+P)/6? Only the schedule activities on critical path or any schedule activity in project?

Regards,
Saeed