When in doubt, stick with the published definition of the word Project, according to PMBOK 5. P.553 states a project is a "temporary endeavor undertaken to create a unique product, service, or result."
Your contract has a start and end date, so that meets the temporary endeavor aspect in the above definition. Now ask yourself, in the temporary time are you creating something unique. You say you are operating something. Then in my opinion, it sounds like an operation, not a project.