TOPIC: Contingency Reserves Vs Management Reserve

Contingency Reserves Vs Management Reserve 1 year 10 months ago #5636

  • Mamadou Issa
  • Mamadou  Issa's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 2
  • Karma: 0
What is the difference between Contingency Reserves and amount of Management Reserve

Thanks

Contingency Reserves Vs Management Reserve 1 year 10 months ago #5638

  • Sarah Burden
  • Sarah Burden's Avatar
  • Offline
  • Junior Boarder
  • Posts: 25
  • Thank you received: 4
  • Karma: 2
Hi Mamadou Issa,

The contingency reserve is controlled by the Project Manager and is part of the budget for the project. The contingency is cover known risks.

the management reserve is held by the management committee and is used for unknown risks. It is not included in the budget for the project. It is held by the management committee and the project manager has to apply to the committee for the funds to be allocated to the project.

Hope that helps.

Sarah
The following user(s) said Thank You: Mamadou Issa

Contingency Reserves Vs Management Reserve 1 year 10 months ago #5641

  • Mamadou Issa
  • Mamadou  Issa's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 2
  • Karma: 0
very clear.. Thanks you Sarah
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Steven Mudrinich, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

×
Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. There are 15 seats left in the class! Learn More...