fbpx

Reply: EAC scenario exam

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : EAC scenario exam

Max. showing the last 6 posts - (Last post first)
8 years 10 months ago #5467

Michael DeCicco

Michael DeCicco's Avatar

Farid,
I'm copying a response to a similiar question that Cornelius Fichtner provided. It is very thorough and can help clarify the overal subject of your question.

Cost and Schedule Formula
Question: A forum member asked for clarification on Estimate at Completion. Cornelius Fichtner Responded. The response discusses in depth the concepts behind some of the cost and schedule formulas.

Response:
From Cornelius Fichtner #4899 December 2014
Response for Scenario 1:
Well, if the question states that the project “MUST” meet the budget, then we shouldn’t be talking about the EAC in the first place. EAC comes into play when we think that we are not going to hit the budget and we need an estimate of the final costs. So I would say such a question would be ambiguous. If meeting the budget is the requirement, we should be considering TCPI as the project’s most important KPI.

We must learn two basic concepts of EAC here: First, we only talk about EAC when we have a feeling that we are not going to hit the budget. Second, we must always remember the EAC “base” formula:

EAC = AC (cost history) + ETC (future costs forecast)
AC is history, you can’t change it, it’s done! ETC is an estimate to complete the rest of the project. Now the question is, how to calculate the ETC? The selection of the formula depends on the situation of the project:

a) If we know things have slipped away in the past (we have spent more than budgeted) but now we are confident that we can meet the budget for the remaining of the activities, we will use the following formula: ETC = BAC – EV; hence EAC = AC + (BAC - EV)

b) If we know that things have slipped away in the past and the slippage is likely to continue at the current cost performance rate, we will use the formula:
EAC = BAC / CPI
Or
EAC = AC + [(BAC – EV)/CPI] …. This formula is not given in PMBOK but it is correct and both formulas will give the exact same results. It can also be proven that one can be derived from the other.

c) If we think project is behind schedule and we need more time to complete the project and due to this delay it will further increase the costs and the CPI is not the only influencing factor, then we use the following formula: EAC = AC + [(BAC-EV) / (CPI * SPI)] …. (This formula is rarely used)

d) Lastly, if we know that our initial estimates were all wrong and there is no way we can predict the final costs based on current performance and budget, we need to work up ETC again from scratch using the bottom up approach.
Response for Scenario 2:

Please don’t be confused that using either CPI or SPI in the EAC calculations helps you achieve any deadline. As I have said earlier, you calculate EAC when you know you are not going to hit the budget and want a new estimate. CPI is brought into the equation when you think that the future costs will be influence by the current performance rate. Similarly SPI will be brought in when you think that the delayed activities will cost you even more since they will now start later and the costs by that time will go up further.

How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum
8 years 10 months ago #5465

Ahmed Amin

Ahmed Amin's Avatar

Hi Farid,

you can review my answer to another thread , I hope it will clarify the topic to you
8 years 10 months ago #5464

Farid Hadj-Hamou

Farid Hadj-Hamou's Avatar

Hello

I appreciate if someone can explain or provide few scenarios where we will use the three different EAC formulas

For example as I was reading one question asking to calaculate the TCPI based on EAC - which I know the formula - The scenario is that the project was half month behind schedule - at six month out of 12 months - and that the project has been working in the red.

That tells me that there is a variance - but did not say if the variance is continuing.

What EAC formula should I use in this case? how do we find the clues in the exam question

I appreciate any inputs - Thank you so much!

Regards
Farid

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login