TOPIC: Query on Flashcard

Query on Flashcard 15 years 3 months ago #388

  • NARAYANAN RAJU
  • NARAYANAN RAJU's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
One of the flash cards (Flashcard # 30) says "When is a fallback plan developed for implementation?". The answer given is "When the selected strategy turns out to be ineffective or if any accepted risk occurs". I personally feel that this answer is not correct. The question specifically asks when the plan is developed, not when it is implemented. I think the right answer should be "In the Planning Process". Any comments from Cornelius or from anyone else??

Re:Query on Flashcard 15 years 3 months ago #389

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 2000
  • Karma: 121
  • Thank you received: 621
Narayanan,

Please take a look at the PMBOK Guide 4th Edition, section 11.5.2 on page 303. This question comes straight from here:

A fallback plan can be developed for implementation if the selected strategy turns out not to be fully effective or if an accepted risk occurs.


A fallback plan is also part of the risk register:

Fallback plans for use as a reaction to a risk that has occurred and the primary response proves to be inadequate;

The important distinction to keep in mind here is that a fallback plan is not a workaround. A workaround is "A response to a negative risk that has occurred", while a fallback plan is developed and implemented if your primary risk response strategy turns out to be ineffective.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Query on Flashcard 15 years 3 months ago #390

  • NARAYANAN RAJU
  • NARAYANAN RAJU's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
I guess there is a very fine line differentiating a workaround and a fallback plan. But as you have rightly said in the past, the PMBOK guide is always right. Thanks, Cornelius, for the clarification.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login