Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Query on Flashcard

Query on Flashcard 7 years 4 months ago #388

  • NARAYANAN RAJU
  • NARAYANAN RAJU's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 3
  • Karma: 0
One of the flash cards (Flashcard # 30) says "When is a fallback plan developed for implementation?". The answer given is "When the selected strategy turns out to be ineffective or if any accepted risk occurs". I personally feel that this answer is not correct. The question specifically asks when the plan is developed, not when it is implemented. I think the right answer should be "In the Planning Process". Any comments from Cornelius or from anyone else??

Re:Query on Flashcard 7 years 4 months ago #389

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Narayanan,

Please take a look at the PMBOK Guide 4th Edition, section 11.5.2 on page 303. This question comes straight from here:
A fallback plan can be developed for implementation if the selected strategy turns out not to be fully effective or if an accepted risk occurs.

A fallback plan is also part of the risk register:
Fallback plans for use as a reaction to a risk that has occurred and the primary response proves to be inadequate;
The important distinction to keep in mind here is that a fallback plan is not a workaround. A workaround is "A response to a negative risk that has occurred", while a fallback plan is developed and implemented if your primary risk response strategy turns out to be ineffective.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Query on Flashcard 7 years 4 months ago #390

  • NARAYANAN RAJU
  • NARAYANAN RAJU's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 3
  • Karma: 0
I guess there is a very fine line differentiating a workaround and a fallback plan. But as you have rightly said in the past, the PMBOK guide is always right. Thanks, Cornelius, for the clarification.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®