Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Create WBS Data Flow

Create WBS Data Flow 2 years 1 week ago #4816

  • James Whelan
  • James Whelan's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
  • Karma: 0
In Fig 5-10. I see Scope baseline going out of Create WBS and into Validate Scope but the Validate Scope Fig 5-15 data flow diagram does not have the Create WBS - scope baseline going into it. why is that?
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 2 years 1 week ago #4817

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
James,

You are correct. It is shown as an explicit output in figure 5-10, but it is not shown explicitly as an input in figure 5-15.

However, it is still there. It is shown as an implicit / implied input.

And now that I've told you this much... let me turn the tables: Can you tell me how the scope baseline is shown as an implicit / implied input in figure 5-15...?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 2 years 1 week ago #4818

  • James Whelan
  • James Whelan's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
  • Karma: 0
as a component of the project management plan.
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 2 years 5 days ago #4838

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar
  • Offline
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
  • Karma: 0
Very Nice question.
IMPOSSIBLE Itself says I M POSSIBLE

Create WBS Data Flow 2 years 3 days ago #4852

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
James - Yes... you got it right!

It is shown as an implicit input as part of the overall PM Plan.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®