TOPIC: Create WBS Data Flow

Create WBS Data Flow 9 years 5 months ago #4816

  • James Whelan
  • James Whelan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
In Fig 5-10. I see Scope baseline going out of Create WBS and into Validate Scope but the Validate Scope Fig 5-15 data flow diagram does not have the Create WBS - scope baseline going into it. why is that?
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 9 years 5 months ago #4817

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
James,

You are correct. It is shown as an explicit output in figure 5-10, but it is not shown explicitly as an input in figure 5-15.

However, it is still there. It is shown as an implicit / implied input.

And now that I've told you this much... let me turn the tables: Can you tell me how the scope baseline is shown as an implicit / implied input in figure 5-15...?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 9 years 5 months ago #4818

  • James Whelan
  • James Whelan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
as a component of the project management plan.
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 9 years 4 months ago #4838

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
Very Nice question.
IMPOSSIBLE Itself says I M POSSIBLE

Create WBS Data Flow 9 years 4 months ago #4852

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
James - Yes... you got it right!

It is shown as an implicit input as part of the overall PM Plan.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login