fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Create WBS Data Flow

Create WBS Data Flow 11 years 7 months ago #4816

  • James Whelan
  • James Whelan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
In Fig 5-10. I see Scope baseline going out of Create WBS and into Validate Scope but the Validate Scope Fig 5-15 data flow diagram does not have the Create WBS - scope baseline going into it. why is that?
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 11 years 7 months ago #4817

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 2066
  • Karma: 142
  • Thank you received: 698
James,

You are correct. It is shown as an explicit output in figure 5-10, but it is not shown explicitly as an input in figure 5-15.

However, it is still there. It is shown as an implicit / implied input.

And now that I've told you this much... let me turn the tables: Can you tell me how the scope baseline is shown as an implicit / implied input in figure 5-15...?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 11 years 7 months ago #4818

  • James Whelan
  • James Whelan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
as a component of the project management plan.
The following user(s) said Thank You: Abhirup Banerjee

Create WBS Data Flow 11 years 7 months ago #4838

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
Very Nice question.
IMPOSSIBLE Itself says I M POSSIBLE

Create WBS Data Flow 11 years 7 months ago #4852

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 2066
  • Karma: 142
  • Thank you received: 698
James - Yes... you got it right!

It is shown as an implicit input as part of the overall PM Plan.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login