Hi Cornelius,
Thank you for getting back to me on this.
There appears to be quite a bit of chatter about section 10.3.1.4 in the PMBOK guide 5th edition. One contributor of the 5th edition even said this is incorrect in the guide. According to the other sections, information such as SV, SPI, CPI are considered Work Performance Information. Therefore, I think the answers B, C, and D are also considered Work Performance Information.
6.7.3 control Schedule: outputs
6.7.3.1 Work Performance Information
The calculated SV and SPI time performance indicators for WBS components, in particular the work packages
and control accounts, are documented and communicated to stakeholders.
7.4.3 control costs: outputs
7.4.3.1 Work Performance Information
The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in particular the work packages and
control accounts, are documented and communicated to stakeholders.