Hello -
Did you get stumped by this question? The Control Quality process has the following eight outputs, one of which is "Organizational Process Updates Assets". The correct answer to this question is "Organizational Process Assets", which is missing the word "Updates", and is therefore not considered an output of the Control Quality process.
Quality Control Measurements
Validated Changes
Verified Deliverables
Organizational Process Assets Updates
Change Requests
Project Management Plan Updates
Project Documents Updates
Work Performance Information
This was a trick question designed to drive home the point that when taking practice exams, as well as the actual exam, you must always "RTFQ" (Read The Full Question", as well as "RTFA" (Read The Full Answers".
I hope this helped.
Happy Studying!
Kevin
Kevin W. Reilly, PMP
Customer Support
OSP International LLC